Deliver DSH LMC and GUI to commission first dish structure, SPF and SPFRx

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • MID ART
    • Hide

      Enable testing of the first dish structure onsite to identify issues and optimisations.

      Show
      Enable testing of the first dish structure onsite to identify issues and optimisations.
    • Hide

      A - FAT of Dish Structure Controller and LMC in the ITF

      B - FAT of LMC to SPFC in ITF

      D - FAT LMC to SPFRx in ITF

      DSH.LMC Reviewed, demo'ed, released for DS Qualification

        • Critical and Major severity bugs addressed
      Show
      A - FAT of Dish Structure Controller and LMC in the ITF B - FAT of LMC to SPFC in ITF D - FAT LMC to SPFRx in ITF DSH.LMC Reviewed, demo'ed, released for DS Qualification Critical and Major severity bugs addressed
    • Inter Program
    • 9
    • 18
    • 0
    • Team_KAROO
    • Sprint 5
    • Hide

      This feature is largely not achieved. 

      See Achieved / Not Achieved flags in the Description field. 

      This feature will be discarded in favour of new features as follows:

      Show
      This feature is largely not achieved.  See Achieved / Not Achieved flags in the Description field.  This feature will be discarded in favour of new features as follows: SP-4351 SP-4352 SP-4117
    • 22.6
    • PI24 - UNCOVERED

    • Team_KAROO
    • Mid G1 Mid G2 Mid G2

    Description

      The first dish is expected to be onsite (TPO-733) during PI21. ACHIEVED

      Dish Structure assembly will take place: NOT ACHIEVED

      • Pedestal, Turnhead, Elevation Assembly, Indexer, Plant Installation, Control System

      Network Connectivity needs to be established (TAIV-841) NOT ACHIEVED

      • Dish Fibre Network (DFN)
      • Dish NSDN Switch
      • Dish LMC (HW and SW)
      • Connectivity to KAPB and Dish Verification System (DVS)

      Dish Structure testing will then commence (TPO-861). NOT ACHIEVED

      Two GUI products are required to support dish structure testing during PI21:

      • DS Qualification SW & GUI (DiSQ) (TAIV-842) is available (Wombat) ACHIEVED
      • Dish AIV Test GUI (DAIGu) (TAIV-788) is available (Karoo) ACHIEVED

      Dish Structure Qualification is expected to commence late in PI22. NOT ACHIEVED

      This feature must ensure that:

      • Both Dish GUI products are fit for purpose to support Dish Structure Testing and Qualification
      • Dish LMC-DS testing in the ITF (A) (TAIV-790) - WIP
      • Dish LMC.SPFC testing in the ITF (B) (TAIV-789) - ACHIEVED
      • Dish LMC.SPFRx testing in the ITF (D) (TAIV-830, TAIV-831) - WIP

      The following commands in the Dish LMC are currently outstanding and are expected to be implemented as part of this Feature:

      • Slew
      • Scan
      • Desired Pointing
      • AchievedPointing

       

      Attachments

        Issue Links

          Structure

            Activity

              People

                s.vrcic Vrcic, Sonja
                r.brederode Brederode, Ray
                Votes:
                0 Vote for this issue
                Watchers:
                6 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (92.41%)

                  Feature Estimate: 9.0

                  IssuesStory Points
                  To Do36.0
                  In Progress   00.0
                  Complete3973.0
                  Total4279.0