Uploaded image for project: 'SAFe Solution'
  1. SAFe Solution
  2. SS-114

Mid-C1: Complete first Mid system integration at the ITF (TAIV-101) and execute the Basic Health and Functionality Verification Event (TAIV-818)

    XporterXMLWordPrintable

Details

    • MID ART, Data Processing, Services, Obs Mgt & Controls
    • Hide

      Reduce risk ahead of product integration on site, identify defects, improve product quality

      Show
      Reduce risk ahead of product integration on site, identify defects, improve product quality
    • Hide

      Integration Readiness Review (TAIV-93) is conducted and indicates that the first System Integration Event (TAIV-101) can proceed.

      Complete the Basic SUT Health and and Functionality Verification Event (TAIV-818) and provide feedback to product development teams (test results, defects, improvements).

      Show
      Integration Readiness Review (TAIV-93) is conducted and indicates that the first System Integration Event (TAIV-101) can proceed. Complete the Basic SUT Health and and Functionality Verification Event (TAIV-818) and provide feedback to product development teams (test results, defects, improvements).
    • 30
    • Sprint 5
    • PI24 - UNCOVERED

    Attachments

      Issue Links

        Features

        Structure

          Activity

            People

              d.gammon Gammon, Donald
              b.mort Mort, Ben
              Votes:
              0 Vote for this issue
              Watchers:
              0 Start watching this issue

              Capability Progress

                Feature Point Burn-up: (54.55%)

                Capability Estimate: 30

                CountFeature Points
                Todo00
                In Progress   20
                Done1312
                Total1522

                Dates

                  Created:
                  Updated:
                  Resolved:

                  Structure Helper Panel