Details
-
Feature
-
Not Assigned
-
None
-
Data Processing
-
-
-
2
-
2
-
8
-
Team_YANDA
-
Sprint 5
-
-
-
-
9.6
-
Stories Completed, Integrated, Outcomes Reviewed, Demonstrated, Satisfies Acceptance Criteria, Accepted by FO
-
-
SPO-545 SPO-725 SPO-863 SPO-878
Description
Follows PSI integration and testing work from PI8 (SP-1291). This is expected to be a largely timeboxed activity and should be coordinated in close collaboration with team VILOA (and Perentie).
Attachments
Issue Links
- depends on
-
SP-1155 Complete integration of visibility receive workflow
- Done
-
SP-1351 Working receive IP address handling
- Done
- relates to
-
SP-1362 Visbility receive (QA) signal display improvements
- Done
-
SP-1434 Improve SDP LMC stability
- Done
-
SP-1476 Facilitate and align activities to achieve end-to-end user test from OET to SDP on PSI Low k8s cluster
- Done
-
SP-1352 SDP PSI usage scenarios documented (and tested)
- Discarded