The MVP should be able to execute multiple scans within a single scheduling block execution, with the system optionally being reconfigured (different CSP setup, different pointing, different scan length, different SDP PBs) between the scans.
This should conform to the design developed in ------ , ADR-3ADR-4 and ADR-10.
This work follows on from SS-37, which was not fully implemented in the last PI. Remaining work to be done:
- Conclude on
ADR-4andADR-10(before start of PI) - Update CSP configure command to use the new configurations found in the PI6 examples: https://confluence.skatelescope.org/display/SWSI/Latest+Version+-+PI6
- Update the CSP scan command to accept the scan id as an argument
- Modify TMC to read the receiveAddresses attribute from SDP and to update CSP configurations with those addresses - split into FSP blocks - before sending them to CSP.
- Address the technical debt accrued in that last PI to work around these issues.
Attachments
Issue Links
- clones
-
SS-37 Enable multi-scan capability in the MVP, including reconfigurations
- Done
- Parent Of
-
SP-999 Decouple SDP-CSP scan configuration (ADR-4 + ADR-10)
- Done
-
SP-1017 OET to adapt to any changes in the JSON configurations resulting from ADR-4 and ADR-10
- Done
-
SP-1039 Adapt TMC to the new receive address design resulting from ADR-10
- Done
-
SP-1104 CSP_Mid.CBF Subarray - implement changes required to support execution of multi-scan Scheduling Blocks (SS-41)
- Done
-
SP-1105 CSP.LMC Subarray - implement changes required to support execution of multi-scan Scheduling Blocks (SS-41)
- Done
- mentioned on
Type | Key | Summary | Status | Assignee | ARTs | Agile Teams | FPs | P | FixVersion | Due Sprint | |
---|---|---|---|---|---|---|---|---|---|---|---|
|
OET to adapt to any changes in the JSON configurations resulting from ADR-4 and ADR-10 |
Done | Bridger, Alan |
Obs Mgt & Controls
|
Team_BUTTONS
|
2 | PI7 | Sprint 1 | |||
|
Done | Wortmann, Peter |
Data Processing
|
Team_SIM
|
2 | PI7 | Sprint 1 | ||||
|
Done | Le Roux, Gerhard [X] (Inactive) |
Obs Mgt & Controls
|
Team_CREAM
|
1 | PI7 | Sprint 1 | ||||
|
Done | Le Roux, Gerhard [X] (Inactive) |
Obs Mgt & Controls
|
Team_CIPA
|
1 | PI7 | Sprint 1 | ||||
|
Adapt TMC to the new receive address design resulting from ADR-10 |
Done | Wortmann, Peter |
Obs Mgt & Controls
|
Team_NCRA
|