Description
Goal: order CLP hardware for AA0.5
- Achieve clarity on hardware order scope
- similar to Alveo purchase: 3 (CLP, s-ITF, Pawsey)*6 +2 Alveos?
- Shared visibility of L3 product BoMs
- Rack vendor/type identified (current Low PSI rack - can't wait for Pawsey rack spec)
- Racks ordered
- CBF servers ordered
- Generic k8s servers ordered