Define System Under Test (SUT 1) for MID PSI

Details

    • Enabler
    • Must have
    • PI12
    • None
    • Services
    • 2
    • 2
    • 0
    • Team_ATLAS
    • Sprint 5
    • Hide
      • The System Integration Test has been defined and shared with the teams;
      • Availability ETA's were gathered as far as possible from software teams, and also
      • discussions were held with the Product Teams regarding roadmaps of all the components;
        • however, there is still some uncertainty related to the readiness of integrated components such as the TMC and OET, and as such not all those dependencies on the OMCPT have been closed off yet - this is also now blocked by two ADR's.
      • Not all the releases' information is available yet - the Release Process is still being developed and will be implemented in PI13 as a result of demands for this from ATLAS Team, VIOLA Team and other stakeholders;
      • The range of system and integration tests have been decided upon, but lots of detailed work is still outstanding and will have to be carried into PI13;
      Show
      The System Integration Test has been defined and shared with the teams; Availability ETA's were gathered as far as possible from software teams, and also discussions were held with the Product Teams regarding roadmaps of all the components; however, there is still some uncertainty related to the readiness of integrated components such as the TMC and OET, and as such not all those dependencies on the OMCPT have been closed off yet - this is also now blocked by two ADR's. Not all the releases' information is available yet - the Release Process is still being developed and will be implemented in PI13 as a result of demands for this from ATLAS Team, VIOLA Team and other stakeholders; The range of system and integration tests have been decided upon, but lots of detailed work is still outstanding and will have to be carried into PI13;
    • 12.6
    • Stories Completed, Outcomes Reviewed, Accepted by FO
    • PI22 - UNCOVERED

    • Team_ATLAS

    Description

      Define System Under Test (SUT 1) for MID PSI, based on product functionality planned to be integrated from the MID AIV Product Integration plan.

      We need to finalise definition of https://confluence.skatelescope.org/display/SE/SP-1773+PSI+Mid+System+Integration+Test+1 as the first Integration Test SUT.

      1. Complete Table info:
        1. Availability ETA
        2. Teams involved
        3. Release versions aimed for SUT
      2. Finalise range of integration and system tests
      3. Update MID Products for SI Plan: https://confluence.skatelescope.org/display/SE/Product+Integration+Flow+Spreadsheet+up+to+AA0.5 

       Importantly, we need to influence the Roadmaps of the DP & OMC ART development work for PI13/14.

      Attachments

        Issue Links

          Structure

            Activity

              People

                a.cremonini Cremonini, Andrea
                A.DeBeer De Beer, Adriaan
                Votes:
                0 Vote for this issue
                Watchers:
                6 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (100.00%)

                  Feature Estimate: 2.0

                  IssuesStory Points
                  To Do00.0
                  In Progress   00.0
                  Complete49.0
                  Total49.0