      Getting ready for Site deployments using correct deployment mechanism is vital. KAROO depend on this as well for DishLMC deployments, as well as PDTs of SPFRx, SPFC.

      Show
      Getting ready for Site deployments using correct deployment mechanism is vital. KAROO depend on this as well for DishLMC deployments, as well as PDTs of SPFRx, SPFC.
    • 3
    • 3
    • 0
    • Team_ATLAS
    • Sprint 5
    • PI24 - UNCOVERED

    • Team_ATLAS
    • Mid G2

    Description

      • Reorganise configuration of SUT deployments, by removing dependency on `Makefile` for configuration, ONLY WHERE SENSIBLE / APPLICABLE:
        • Define environment specific static configuration in `values.yaml` only
        • Migrate all dynamic configuration done in Makefiles into `VAULT`
      • Setup FluxCD Kustomizations for deploying HelmReleases of DishLMC, SPFRx deployer etc to DishLMC HW in ITF, and "SUT chart contents" to the Telescope Manager cluster in ITF (TangoDB, TMC, CSPLMC, CBFMCS, SDP Deployer, EDA, AlarmHandler (product decision TBD), CIA).
      • Use FluxCD Kustomizations / HelmReleases for deployments into Mid ITF, including DishLMC instances (namespaced or VM based)
      • Confirm that SUT deployments work as expected in ITF using FluxCD, by using Smoke test suite (see SP-4666)

      Attachments

        Issue Links

          Structure

            Activity

              People

                s.vrcic Vrcic, Sonja
                A.DeBeer De Beer, Adriaan
                Votes:
                0 Vote for this issue
                Watchers:
                0 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (0%)

                  Feature Estimate: 3.0

                  IssuesStory Points
                  To Do00.0
                  In Progress   00.0
                  Complete00.0
                  Total00.0