Mid.CBF 4-Receptor Correlator part 3

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • MID ART
    • Hide

      A reliable 4-receptor correlator is core functionality that is needed for a functional AA0.5 SKA telescope.

      Show
      A reliable 4-receptor correlator is core functionality that is needed for a functional AA0.5 SKA telescope.
    • Hide
      • Test_6 consistently passing
      • The nightly integration tests are updated to include a stable, passing single test with correlation on 4 VCCs and 4 FSPs (as defined by CIP-1992)
      • The Mid.CBF HPS FSP application has been refactored:
        • Refactor to use VCC IDs rather than "receptors" - CIP-1766
        • Configure system with unique FSP IDs
        • Remove FSP receptor lane logic and rely on SLIM
      • Deliver TAIV-19:
        • Updated FW and SW
        • FAT results provided
        • SAT Training provided.
      Show
      Test_6 consistently passing The nightly integration tests are updated to include a stable, passing single test with correlation on 4 VCCs and 4 FSPs (as defined by CIP-1992) The Mid.CBF HPS FSP application has been refactored: Refactor to use VCC IDs rather than "receptors" - CIP-1766 Configure system with unique FSP IDs Remove FSP receptor lane logic and rely on SLIM Deliver TAIV-19: Updated FW and SW FAT results provided SAT Training provided.
    • 6
    • 6
    • 0
    • Team_CIPA
    • Sprint 5
    • 22.6
    • PI24 - UNCOVERED

    • Mid.CBF_SW Team_CIPA
    • Mid G1

    Description

      Continuation of SP-3839

      Implement a stable and reliable 4-receptor correlator (4 VCCs, 4 FSP) and verify it using the parameterized automated test framework. Note: this is a happy path only, and does not include detailed signal chain verification.

      The flow of data for the happy path test of this correlator can be summarized as:

      Includes:

      • Addressing known bugs with the CBF and parameterized test framework
      • Adding the above happy path test to the PSI CBF nightly regression tests and getting it consistently passing
      • Updating the TMC Simulator to support multiple delay models

      Attachments

        Issue Links

          Structure

            Activity

              People

                J.Roy Roy, Jayashree
                R.Huxtable Huxtable, Robert
                Votes:
                0 Vote for this issue
                Watchers:
                0 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (0%)

                  Feature Estimate: 6.0

                  IssuesStory Points
                  To Do00.0
                  In Progress   30.0
                  Complete10.0
                  Total40.0