Details
-
Enabler
-
Could have
-
Obs Mgt & Controls
-
-
-
3
-
3
-
0
-
Team_CIPA
-
Sprint 5
-
-
-
-
19.6
-
Stories Completed, Solution Intent Updated, Outcomes Reviewed, NFRS met, Demonstrated, Satisfies Acceptance Criteria, Accepted by FO
-
-
Team_CIPA
Description
Initial AA1 PST beamformer design work, with the following activities:
- Review Mid CBF software documentation, and update as required to reflect current implementation
- Carry out PST beamformer software design for AA1.0, with CDR design and current implementation as inputs
- Identify risks, and any areas that require further investigation and design effort
- Propose a development plan for AA1 software