Obs Mgt & Controls
-
- Show good understanding of CSP-Low
- Fulfill contractual obligations
- Identify potential issues in processes and requirements
-
7
-
7
-
0
-
Team_TOPIC
-
Sprint 5
-
-
-
-
19.6
-
Stories Completed, Accepted by FO
-
-
Team_TOPIC
Description
SRR preparation
- Deliver the SRR document set
- See PI#19 SRR deliverables spreadsheet: https://topicbv.sharepoint.com/:x:/s/SKACSPInternal/ESgD8SYoujNIvzhhC0fkviABLW4E6QiKjBgMYMtP-XJ4Gg?e=zDTm58
--> SEMP, PRS L2, Verification Plan, MAIT Plan, ECM Control Plan
- See PI#19 SRR deliverables spreadsheet: https://topicbv.sharepoint.com/:x:/s/SKACSPInternal/ESgD8SYoujNIvzhhC0fkviABLW4E6QiKjBgMYMtP-XJ4Gg?e=zDTm58
Rob to set up meeting with Jacque to define how the CSP Low SRR will be conducted in PI#19.