Begin MID Long Haul Transmission Procurement

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Feature
    • Must have
    • PI18
    • MID Networks
    • None
    • Services
    • Hide

      Analysis of responses and support of recommendations will help facilitate successful contract award

      Show
      Analysis of responses and support of recommendations will help facilitate successful contract award
    • Hide
      • Get to the PQQ stage (PQQ launched)
      • Respond to any queries received during the PI
      • Evaluate any responses received during the PI

       

      (Remainder of procurement flow to be covered under a future feature)

      Show
      Get to the PQQ stage (PQQ launched) Respond to any queries received during the PI Evaluate any responses received during the PI   (Remainder of procurement flow to be covered under a future feature)
    • 3
    • 3
    • 0
    • Team_SKANET
    • Sprint 5
    • Hide

      Due to changes to the procurement plan we did not reach PQQ this PI, that will be covered under a new feature SP-3385.
      Technical inputs to market survey and tech spec provided to and accepted by networks PM. Documents not yet complete to link here

      Show
      Due to changes to the procurement plan we did not reach PQQ this PI, that will be covered under a new feature SP-3385 . Technical inputs to market survey and tech spec provided to and accepted by networks PM. Documents not yet complete to link here
    • 18.6
    • Stories Completed, Satisfies Acceptance Criteria, Accepted by FO
    • PI23 - UNCOVERED

    Description

      Support the tender process for MID MID Long Haul Transmission.

      Involves getting to the PQQ (PQQ launched) stage and dealing with any queries/responses received during this PI.

       

      (Detailed analysis of tenderers submissions, scoring, reconciliation, collation to summary for use by TSC toward award proposals to be covered under a future feature once procurement reaches that stage)

      Attachments

        Structure

          Activity

            People

              m.deegan Deegan, Miles
              pete.shephard Shephard, Pete [X] (Inactive)
              Votes:
              0 Vote for this issue
              Watchers:
              0 Start watching this issue

              Feature Progress

                Story Point Burn-up: (100.00%)

                Feature Estimate: 3.0

                IssuesStory Points
                To Do00.0
                In Progress   00.0
                Complete27.0
                Total27.0