Rewrite documentation for MID Long Haul Design

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Feature
    • Must have
    • PI15, PI16
    • None
    • None
    • Services
    • Hide

      So much has changed on the MID design that the baseline document is completely incorrect. A number of contracts both within and outside of networks reference the design so we need to amend this design completely and document it. We have a short term resource who can take this on now. This design will incorporate the designs for AA0.5,1,2,3*4 which will then make it more simple for Jas to update netterrain for MID as Anthony Brown our resource for MID is leaving and Jas will not have the time to do both in the required timescales. This  will reduce Jas's workload as he takes on management of Netterrain from Sam LLoyd.

      Show
      So much has changed on the MID design that the baseline document is completely incorrect. A number of contracts both within and outside of networks reference the design so we need to amend this design completely and document it. We have a short term resource who can take this on now. This design will incorporate the designs for AA0.5,1,2,3*4 which will then make it more simple for Jas to update netterrain for MID as Anthony Brown our resource for MID is leaving and Jas will not have the time to do both in the required timescales. This  will reduce Jas's workload as he takes on management of Netterrain from Sam LLoyd.
    • Hide

      A document that can be used as a baseline document for the MID Design and will collect the information for netterrain updates and be a contractual refernce until netterrain is updated.

      Show
      A document that can be used as a baseline document for the MID Design and will collect the information for netterrain updates and be a contractual refernce until netterrain is updated.
    • Inter Program
    • 1.5
    • 1.5
    • 0
    • Team_SKANET
    • Sprint 5
    • Hide

      Defined baseline design for MID for Aa0.5,1,2,3*,4

      Documents produced, reviewed by stakeholders, and signed off by PO

      Show
      Defined baseline design for MID for Aa0.5,1,2,3*,4 Documents produced, reviewed by stakeholders, and signed off by PO
    • 16.6
    • Stories Completed, Integrated, Satisfies Acceptance Criteria
    • PI22 - UNCOVERED

    Description

      Due to ECP 2000048 and ECP 210134 the design for the MID long hual has changed and needs to be recorded in a document as the baseline design. Also we need the document to incorporate the design at AA0.5, AA1, AA2, AA3* . The work for this document will be the pre-cursor for netterain to be updated as the single source of truth. 

      Attachments

        Issue Links

          Structure

            Activity

              People

                j.muller Muller, Jaco
                j.hammond Hammond, Jill
                Votes:
                0 Vote for this issue
                Watchers:
                0 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (100.00%)

                  Feature Estimate: 1.5

                  IssuesStory Points
                  To Do00.0
                  In Progress   00.0
                  Complete34.0
                  Total34.0