This Feature captures VIOLA's contribution to SPO-1059 as follows:
- Coordinate the receiving of new equipment (2 new TPMs v1.6, subrack, etc), and its installation and connection in PSI Low. This includes configuring the network as needed, and purchasing a 40G cable as needed to connect TPMs to CBF. This will involve a close collaboration with the MCCS and Perentie teams.
- Record all new HW received and installed, including SW, in the PSI Low configuration table and diagram. This includes both the TPM equipment but also any other HW that is installed, such as CBF, PST. Once all the new equipment is recorded, the configuration table and diagram should be reviewed and released.
- Determine what additional equipment is needed in PI#11, such as the 100G switch. If needed, make a plan to procure this.