Develop a Process for Expanding NetTerrain Access to the MID Infrastructure Team

Details

    • Enabler
    • Not Assigned
    • PI7
    • None
    • Services
    • Hide

      A MID Infrastructure NetTerrain Administrator has been identified and agreed. A process document has been created that defines how the MID Infrastructure NetTerrain Administrator should use NetTerrain.

      Show
      A MID Infrastructure NetTerrain Administrator has been identified and agreed. A process document has been created that defines how the MID Infrastructure NetTerrain Administrator should use NetTerrain.
    • 2
    • 2
    • 0
    • Team_PLANET
    • Sprint 4
    • Hide

      A NetTerrain Process Document has been created and is currently uner review by the Configuration Manager. The current draft of this document has been attached to this ticket.

      Document is now in ALIM: ALIM Link

      Show
      A NetTerrain Process Document has been created and is currently uner review by the Configuration Manager. The current draft of this document has been attached to this ticket. Document is now in ALIM:  ALIM Link
    • 8.1
    • Accepted by FO
    • PI22 - UNCOVERED

    • Team_PLANET

    Description

      We want to extend the editing ability of NetTerrain to the MID Infrastructure Team to allow them to manage their own design area and add the MeerKAT extension project, but we need a way of managing how changes are made and controlled. We need to:

      • Identify a suitable MID Infrastructure NetTerrain Administrator
      • Identify the administrative boundaries of this administrator (what will the administrator be responsible for and identify the demarcation)
      • Identify which pages in NetTerrain this administrator requires access to and identify if access can be restricted to certain areas to minimise mistakes.
      • Identify what information will be added initially (CDR Baselines Design?) and what the change control process is for updating the design.
      • Identify if the NetTerrain standards document is suitable to be distributed.
      • Identify what training will be provided and by whom.
      • Create a process/procedural document that defines how the MID Infrastructure NetTerrain Administrator should use NetTerrain.

      Attachments

        Issue Links

          Structure

            Activity

              People

                j.santander-vela Santander-Vela, Juande
                s.lloyd Lloyd, Sam
                Votes:
                0 Vote for this issue
                Watchers:
                8 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (100.00%)

                  Feature Estimate: 2.0

                  IssuesStory Points
                  To Do00.0
                  In Progress   00.0
                  Complete34.0
                  Total34.0