Uploaded image for project: 'SAFe Program'
  1. SAFe Program
  2. SP-967

Purchase Servers PSI

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Obs Mgt & Controls
    • Hide
      • extension of Low PSI to include control equipment and software 
      • enables wider testing of the control chain with the signal chain 
      • enables future software deployment testing 
      • secondary location for testing of equipment
      • MVP can test actual hardware - not just simulators 
      Show
      extension of Low PSI to include control equipment and software  enables wider testing of the control chain with the signal chain  enables future software deployment testing  secondary location for testing of equipment MVP can test actual hardware - not just simulators 
      • agreement on what hardware is to be ordered
      • hardware is procured and installed in the Low PSI
      • access is enable to appropriate first users 
    • 1.375
    • 1.375
    • 5.818
    • Team_PERENTIE
    • Sprint 5
    • Hide

      The Low PSI servers are procured, installed and operational in the Low PSI.
      The feature was demonstrated at system demo: https://docs.google.com/presentation/d/1jPf5YtFwidk3Zh3B5ZsSv4UI6rw-Rn9xClYNIgv9TmM/edit#slide=id.g6f78837634_1_57

      Show
      The Low PSI servers are procured, installed and operational in the Low PSI. The feature was demonstrated at system demo: https://docs.google.com/presentation/d/1jPf5YtFwidk3Zh3B5ZsSv4UI6rw-Rn9xClYNIgv9TmM/edit#slide=id.g6f78837634_1_57
    • 9.4
    • Stories Completed, Integrated, Solution Intent Updated, BDD Testing Passes (no errors), Outcomes Reviewed, NFRS met, Demonstrated, Satisfies Acceptance Criteria, Accepted by FO
    • PI23 - UNCOVERED

    • CSP_Low.CBF PSI SYSTEM_DEMO_3 Team_PERENTIE
    • SPO-559

    Attachments

      Issue Links

        Structure

          Activity

            People

              m.deegan Deegan, Miles
              y.chen Chen, Yuqing
              Votes:
              0 Vote for this issue
              Watchers:
              7 Start watching this issue

              Feature Progress

                Story Point Burn-up: (100.00%)

                Feature Estimate: 1.375

                IssuesStory Points
                To Do00.0
                In Progress   00.0
                Complete611.0
                Total611.0

                Dates

                  Created:
                  Updated:
                  Resolved:

                  Structure Helper Panel