Finalise analysis on CBF.Low "enhanced" architecture for engineering sub-array

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Obs Mgt & Controls
    • Hide
      • far greater reliability and availability
      • improved compliance compared to current design (all requirements compliant)
      • The new design has a smoother rollout
      • Cost can be reduced by reducing stations or bandwidth
      • It is possible to create an engineering subarray with little impact on the system (and possibly none - TBD)
      • There is a reduction in number of Gemini = 12 x (10+9) + 43 = 271
      Show
      far greater reliability and availability improved compliance compared to current design (all requirements compliant) The new design has a smoother rollout Cost can be reduced by reducing stations or bandwidth It is possible to create an engineering subarray with little impact on the system (and possibly none - TBD) There is a reduction in number of Gemini = 12 x (10+9) + 43 = 271
      • ECP raised with the all analysis needed
    • 1.1
    • 1.5
    • 27.273
    • Team_PERENTIE
    • Sprint 4
    • Show
      Word file attached describing the dynamic operation. Also 3 presentations in which this is discussed. 16th Apr 2020: Perentie LMC Architecture https://docs.google.com/presentation/d/1wyA80vUTwOG-eQZ0fWCJXz3pX51oF-ekWp-Vy8n07RQ/edit#slide=id.g72e68ff938_12_138 12th Feb 2020: SP-725 Perentie Engineering Subarray https://docs.google.com/presentation/d/1uDT1daAohLt9IC8FOSTTdNws2fmqOyngIr8ynHNCuNI/edit#slide=id.g6f78837634_1_5 18th Oct 2019: SP-537 Subarray Investigation https://docs.google.com/presentation/d/1JOLejvE9SKgCfJSePwzyXm0MRUfJvpLFn2Ghr7B18Xo/edit#slide=id.g5d4610ddd4_0_0
    • 7.5
    • PI22 - UNCOVERED

    Description

      Finalise analysis of the "enhanced CBF architecture" which includes negotiations (where SKAO will be involved) with LFAA on impact on ICDs and the feasibility of the ICD changes required. With the analysis material generated, an ECP has to be be raised during PI6 and further assessment requests as part of the ECP process should be taken onboard.

      Attachments

        Structure

          Activity

            People

              b.alachkar Alachkar, Bassem
              m.labate Labate, Maria Grazia
              Votes:
              0 Vote for this issue
              Watchers:
              5 Start watching this issue

              Feature Progress

                Story Point Burn-up: (100.00%)

                Feature Estimate: 1.1

                IssuesStory Points
                To Do00.0
                In Progress   00.0
                Complete618.0
                Total618.0