Make preparations to be able to integrate PSS receiver into the SDP MVP

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Data Processing
    • Hide

      Adds additional PSS functionality to MVP.

      Show
      Adds additional PSS functionality to MVP.
    • Hide

      Given – Dummy pulsar search data needs to be generated
      When — the PSS-SDP interface is to be tested
      Then — Dummy data can be generated and fed to PSS SDP exporter

      Show
      Given – Dummy pulsar search data needs to be generated When — the PSS-SDP interface is to be tested Then — Dummy data can be generated and fed to PSS SDP exporter
    • 2
    • 2
    • 6.5
    • Team_PSS
    • Sprint 5
    • Hide

      Insert links to relevant docs and / or code here:

      A single-pulse search dummy data product emulator is currently being built within the PSS pipeline.

      https://gitlab.com/SKA-TDT/cheetah/-/tree/sps_emulator

      Show
      Insert links to relevant docs and / or code here: A single-pulse search dummy data product emulator is currently being built within the PSS pipeline. https://gitlab.com/SKA-TDT/cheetah/-/tree/sps_emulator
    • 6.6
    • PI22 - UNCOVERED

    Description

      Integrates the current PSS pipeline (Cheetah) PSS receiver into the existing SDP pss-receive infrastructure.

      The Objective is to make initial preparations to allow the development of the PSS-SDP interface in PI7. Preparations include:

      • Designated developer of this interface (Ben Shaw) improving understanding of C++ and the PSS pipeline, Cheetah
      • Create capability to generate dummy PSS science data and export it to SDP by setting up Single Pulse Search (SPS) generator, PSS pipeline (Cheetah) and C++ wrapper for data generator

      Attachments

        Structure

          Activity

            People

              b.mort Mort, Ben
              m.pearson Pearson, Mike [X] (Inactive)
              Votes:
              0 Vote for this issue
              Watchers:
              0 Start watching this issue

              Feature Progress

                Story Point Burn-up: (100.00%)

                Feature Estimate: 2.0

                IssuesStory Points
                To Do00.0
                In Progress   00.0
                Complete623.0
                Total623.0

                Dates

                  Created:
                  Updated:
                  Resolved:

                  Structure Helper Panel