SKAO network separation from JBO

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Hide

      Network separation from UMAN will allow the SKA Observatory to have full control of its network infrastructure.

      Show
      Network separation from UMAN will allow the SKA Observatory to have full control of its network infrastructure.
    • Hide

      Design report reviewed by stakeholders:

      • IT (Paul Furness)
      • Feature Owner (@Rees, Nick)
      Show
      Design report reviewed by stakeholders: IT (Paul Furness) Feature Owner (@Rees, Nick)
    • 2
    • 2
    • 6.5
    • Team_SKANET
    • Hide

      Old feature; outcomes not easy to locate; cloned to SP-141.

      Show
      Old feature; outcomes not easy to locate; cloned to SP-141 .
    • 10.6
    • Accepted by FO
    • PI24 - UNCOVERED

    • Iteration_5 Team_SKANET

    Description

      The SKA Observatory networks need to be independent from the UMAN networks before the SKA Observatory reaches IGO status. The SKA Observatory must have full control of their network infrastructure. The SKA Observatory will rely heavily on external connectivity to the telescope sites and cloud resources, and therefore requires a reliable and stable connection to the outside world.

      Work with UMAN and JISC to define a number of options that will allow all entities at the Jodrell Bank Observatory to have redundant and reliable external connectivity whilst allowing the SKA Observatory to become independent of the UMAN network infrastructure.

      Create a document that describes each option, and its associated costs, and include a recommended solution.

      Attachments

        Issue Links

          Structure

            Activity

              People

                n.rees Rees, Nick
                n.rees Rees, Nick
                Votes:
                0 Vote for this issue
                Watchers:
                0 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (100.00%)

                  Feature Estimate: 2.0

                  IssuesStory Points
                  To Do00.0
                  In Progress   00.0
                  Complete65.0
                  Total65.0