- Avoid the big bang approach to integration
- Get to know the LFAA hardware, firmware and software - reduce surprises
- Data of any sort can start flowing between LFAA and CSP
-
1.6
-
3
-
21.875
-
Team_PERENTIE
-
Sprint 1
-
-
-
6.2
Description
- As part of the end-to-end signal chain goal Perentie is going to install the first TPM into the Low PSI facility at CSIRO.
- Perentie don't know exactly what we are going to receive as yet - so the bar is set low for integration goals (getting it and powering it may be a fallback goal).
- We hope to establish an optical link between the TPM and the Gemini card.