  2. SP-4683

At least 4 SRCs will meet *full* v0.1 storage, compute and network requirements in time

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Epic
    • Must have
    • PI24
    • None
    • None
    • v0.1 Infrastructure Requirements
    • SRCnet
    • Hide

      If we can show that by the end of PI24 we at least 4 sites globally will be able to deliver the required v0.1 infrastructure, then we will be able to confidently move forward with 0.1 test campaigns.

      This epic gathers the underlying features into one feature family, of which there are 9 planned v0.1 nodes

      Show
      If we can show that by the end of PI24 we at least 4 sites globally will be able to deliver the required v0.1 infrastructure, then we will be able to confidently move forward with 0.1 test campaigns. This epic gathers the underlying features into one feature family, of which there are 9 planned v0.1 nodes
    • 0
    • Hide

      See underlying features. At least 4 are complete.

      Show
      See underlying features. At least 4 are complete.

    Attachments

      Issue Links

        Structure

          Activity

            People

              J.DeBoer De Boer, Janneke
              Robert.Perry Perry, Robert
              Votes:
              0 Vote for this issue
              Watchers:
              0 Start watching this issue

              Dates

                Created:
                Updated:

                Structure Helper Panel