Uploaded image for project: 'SAFe Program'
  1. SAFe Program
  2. SP-4601

PST voltage data capture end-to-end on DS-PSI

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Feature
    • High
    • PI24
    • LOW CSP
    • None
    • LOW ART
    • Hide

      In order to complete the LOW CSP AA0.5 milestone PST should be integrated and delivered to AIV.

      After interferometry, SS-155, formation and capture of complex voltage tied-array beamformed data for a single on-axis beam is the 2nd array-level mode being rolled out for AA0.5.

      Show
      In order to complete the LOW CSP AA0.5 milestone PST should be integrated and delivered to AIV. After interferometry,  SS-155 , formation and capture of complex voltage tied-array beamformed data for a single on-axis beam is the 2nd array-level mode being rolled out for AA0.5.
    • Hide

      To have full end-to-end integration of PST with the latest release versions of the (applicable) sub-systems. Complete data flow between LMC->CBF->PST without any hardcoded values and special configurations. 

      Generate PST data products that PST team can successfully analyze. We have dependency on other teams to reach the result.

      Show
      To have full end-to-end integration of PST with the latest release versions of the (applicable) sub-systems. Complete data flow between LMC->CBF->PST without any hardcoded values and special configurations.  Generate PST data products that PST team can successfully analyze. We have dependency on other teams to reach the result.
    • 6
    • 4
    • 0
    • Team_TOPIC
    • Sprint 4
    • PI24 - UNCOVERED

    • Low G5

    Description

      (Goal 5) PST voltage recorder end-to-end integration

      Objective:

      PST is part of the LOW CSP AA0.5 delivery, as agreed prior to the LOW CSP AA0.5 FAT/SAT, LOW CSP will integrate PST in PI#24.

      At LOW PSI it was shown that between LMC, PST and CBF dataflow can be obtained, however this was done on a lower level and it contained hardcoded values, and was done with earlier (development) versions of LMC, CBF and PST. More specifically CBF was configured to send one SPS channel data to a specified IP and port.

       

      Aim:

      To have full end-to-end integration of PST with the latest release versions of the (applicable) sub-systems. Complete data flow between LMC->CBF->PST without any hardcoded values and special configurations. 

      Generate PST data products that PST team can successfully analyze. We have dependency on other teams to reach the result.

      Business value:

      In order to complete the LOW CSP AA0.5 milestone PST should be integrated and delivered to AIV.

      After interferometry, SS-155, formation and capture of complex voltage tied-array beamformed data for a single on-axis beam is the 2nd array-level mode being rolled out for AA0.5.

      Attachments

        Issue Links

          Structure

            Activity

              People

                Hariharan.Krishnan Krishnan, Hariharan
                R.vanRooyen van Rooyen, Ruby
                Votes:
                0 Vote for this issue
                Watchers:
                0 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (80.00%)

                  Feature Estimate: 6.0

                  IssuesStory Points
                  To Do24.0
                  In Progress   00.0
                  Complete816.0
                  Total1020.0

                  Dates

                    Created:
                    Updated:

                    Structure Helper Panel