Uploaded image for project: 'SAFe Program'
  1. SAFe Program
  2. SP-4576

CSP LMC: Investigate and create migration plan for new test harness uptake

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Obs Mgt & Controls
    • Hide

      we have a plan for adoption of ITH 

      Show
      we have a plan for adoption of ITH 
    • Hide
      • decisions have been made as to what old or new tests are candidates to rely on the new test harness
      • an analysis has been done and reported as to what additions are needed to the test harness (what new facades, wrappers, actions, configs, inputs) to support those tests; 
        • the analysis should identify (not define) these additions and be detailed enough to estimate the needed effort
      • based on such an analysis we (Emanuele, Giorgio, Verity) will identify the structural limits and possible solutions for the TH seen as a platform
      Show
      decisions have been made as to what old or new tests are candidates to rely on the new test harness an analysis has been done and reported as to what additions are needed to the test harness (what new facades, wrappers, actions, configs, inputs) to support those tests;  the analysis should identify (not define) these additions and be detailed enough to estimate the needed effort based on such an analysis we (Emanuele, Giorgio, Verity) will identify the structural limits and possible solutions for the TH seen as a platform
    • 0.5
    • 0.5
    • 0
    • Team_CREAM
    • Sprint 5
    • testing

    Description

      Attachments

        Issue Links

          Structure

            Activity

              People

                g.brajnik Brajnik, Giorgio
                Adam.Avison Avison, Adam
                Votes:
                0 Vote for this issue
                Watchers:
                1 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (0%)

                  Feature Estimate: 0.5

                  IssuesStory Points
                  To Do00.0
                  In Progress   13.0
                  Complete00.0
                  Total13.0

                  Dates