      Safely turning off the telescope from any state and bringing it to a known operational state is very important as the telescope is built in a remote location.
      We need to make sure the basic operation of the telescope, the power consumption during operation is within the acceptable range, alarms are propagated correctly and signal displays are show correct data.

      Show
      Safely turning off the telescope from any state and bringing it to a known operational state is very important as the telescope is built in a remote location. We need to make sure the basic operation of the telescope, the power consumption during operation is within the acceptable range, alarms are propagated correctly and signal displays are show correct data.
    • Hide

      All the test cases are executed.
      Bugs identified are reported in proper channels (SKB, SPRTS)
      Test results are captured and updated in the test reports.

      Show
      All the test cases are executed. Bugs identified are reported in proper channels (SKB, SPRTS) Test results are captured and updated in the test reports.
    • Inter Program
    • 2
    • 2
    • 0
    • Team_VULCAN
    • Sprint 5
    • PI23 - UNCOVERED

    • Team_VULCAN

    Description

      TC.L.ITF.2.1.1 Power Modes
      TC.L.ITF.2.1.8 Signal Displays
      TC.L.ITF.2.1.9 System Alarms & Failures
      TC.L.ITF.2.1.5 Power Interruption (This is added late to the scope, but no additional support should be needed from the team)

      TC.L.ITF.2.1.11 Software Maintenance and Updates

      TC.L.ITF.2.2.2 Observation Metadata - observation under OSO control TMC Control

      Provide Jupyter NB for the test case with some steps consisting of starting up the telescope, performing a mock observation and shutting down the telescope.
      AIV portal, MCCS's power spectra displays and SDP displays will be used for Real-time signal displays that show the signal processing products.

      Open items to be clarified:

      • TC.L.ITF.2.1.8 Signal Displays: Possibility of a feature for MCCS to implement dynamic histograms of sample voltages for all the samplers of a selected station
      • TC.L.ITF.2.1.9 System Alarms & Failures - Alarm Handler is being developed by TMC in PI22, which needs to be consumed by the subsystem teams to configure alarms of their own subsystems. Finally AIV can use the system to verify that the triggered alarms are displayed correctly. Need clarification as to where are these alarms displayed, on the Taranta Dashboards or another UI is there? Depending on when the functionality is made available, this test case may become out of scope for PI22.

      Note:

      • TMC does not provide power consumption displays.
      • Standby mode (Low Power mode) is not supported by all the subsystems yet. So, the test will just measure the power consumption as it is.

      Attachments

        Issue Links

          Structure

            Activity

              People

                Vani.Naram Naram, Vani
                Vani.Naram Naram, Vani
                Votes:
                0 Vote for this issue
                Watchers:
                0 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (0%)

                  Feature Estimate: 2.0

                  IssuesStory Points
                  To Do00.0
                  In Progress   00.0
                  Complete00.0
                  Total00.0

                  Dates

                    Created:
                    Updated:

                    Structure Helper Panel