    • Obs Mgt & Controls
      • Reintroduces and makes visible the testing of the OET to TMC interface.
      • Builds confidence in the ability to deploy a fully integrated system.
    • Hide
      • A Xray Test Plan covering OET <-> TMC interfaces is available in JIRA. 
      • The Test Plan covers the full SKAO ObsState model.
      • The test plan is executed against the OSO's TMC simulator, in the OSO integration environment.
      • The Test plan is executed against the real TMC (with subordinate subsystems mocked out).
      Show
      A Xray Test Plan covering OET <-> TMC interfaces is available in JIRA.  The Test Plan covers the full SKAO ObsState model. The test plan is executed against the OSO's TMC simulator, in the OSO integration environment. The Test plan is executed against the real TMC (with subordinate subsystems mocked out).
    • 3
    • 3
    • 0
    • Team_BUTTONS
    • Sprint 5
    • Hide
      • Most work here has been expended on creating a new OSO project: ska-oso-tmc-integration-tests. The idea is that will contain the test machinery (OSO's own TMC Simulator (state machine) and real TMC running in simulated mode. OSO Scripting can import this project and use it to test its scripting functions
      • In terms of actual work done, the new project was created and the TMC Simulator was moved into this from OSO Scripting. An existing BDD test (pointing calibration) now runs within this new testing framework. It hasn't been possible to get this running against 'real' TMC.
      Show
      Most work here has been expended on creating a new OSO project: ska-oso-tmc-integration-tests. The idea is that will contain the test machinery (OSO's own TMC Simulator (state machine) and real TMC running in simulated mode. OSO Scripting can import this project and use it to test its scripting functions In terms of actual work done, the new project was created and the TMC Simulator was moved into this from OSO Scripting. An existing BDD test (pointing calibration) now runs within this new testing framework. It hasn't been possible to get this running against 'real' TMC.
    • PI23 - UNCOVERED

    • Team_BUTTONS

    Description

      By the end of PI22 an Xray Test plan (and associated BDD Tests) covering the full ObsState model exist for testing the interface between the OET and TMC.

      Attachments

        Issue Links

          Structure

            Activity

              People

                Adam.Avison Avison, Adam
                Adam.Avison Avison, Adam
                Votes:
                0 Vote for this issue
                Watchers:
                2 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (60.00%)

                  Feature Estimate: 3.0

                  IssuesStory Points
                  To Do12.0
                  In Progress   00.0
                  Complete13.0
                  Total25.0