Uploaded image for project: 'SAFe Program'
  1. SAFe Program
  2. SP-4039

Support AA0.5 & AA1 commissioning of SDP and prepare the SDP system for AA2+

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Epic
    • Not Assigned
    • None
    • COM SDP SW
    • None
    • SDP AA0.5 & AA1 commissioning
    • Data Processing
    • 0
    • Hide
      • We have supported AA0.5 and AA1 commissioning.
      • We have all important instrumental calibration pipelines integrated with the control system and services, and ready for AA2 commissioning.
      • We have prepared the operational system (receive, instrumental calibration pipelines, control system and services) for AA2+ scale.
      Show
      We have supported AA0.5 and AA1 commissioning. We have all important instrumental calibration pipelines integrated with the control system and services, and ready for AA2 commissioning. We have prepared the operational system (receive, instrumental calibration pipelines, control system and services) for AA2+ scale.

    Description

      Support AA0.5 and AA1 commissioning with control system and pipeline development/scaling as needed. This will also cover development of pipelines that require heavy system interaction (primarily instrumental calibration) to be ready to support AA2 commissioning. These will require scaling to AA2 as part of this development. Development of required control system and services.

      Attachments

        Structure

          Activity

            People

              m.ashdown Ashdown, Mark
              m.ashdown Ashdown, Mark
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

              Dates

                Created:
                Updated:

                Structure Helper Panel