Migration of Canfar Science platform to kubernetes cluster on SWESRC OpenStack

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • SRCnet
    • Hide

      This way we will have all services in one place. With this feature, the SRCNet will count with a computing infrastructure focused on prototyping activities and flexible enough to develop and test new tools. 

      Show
      This way we will have all services in one place. With this feature, the SRCNet will count with a computing infrastructure focused on prototyping activities and flexible enough to develop and test new tools. 
    • Hide

      AC1: The CANFAR science platform instance at SWESRC is successfully migrated and able to accept users logging in using SRC IAM.

      Show
      AC1: The CANFAR science platform instance at SWESRC is successfully migrated and able to accept users logging in using SRC IAM.
    • Intra Program
    • 2
    • 2
    • 0
    • Team_CORAL
    • Sprint 4
    • Hide

      Migration will not be completed during PI22 due to delays in receiving the software and issues with the configuration, specially with network configuration. 

      Show
      Migration will not be completed during PI22 due to delays in receiving the software and issues with the configuration, specially with network configuration. 
    • PI24 - UNCOVERED

    • PI24-PB science-platform-services technical_debt

    Description

       

      Update 2 Sep 2024: OpenStack deployment is done. Currently finishing K8s deployment, dealing with clusterAPI issues.

       

      The currently running Canfar Science platform will be redeployed on the kubernetes cluster in the SWESRC OpenStack cloud. Deployment of, and migration to, a new computing infrastructure is needed in order to maintain the Swedish site capabilities towards SRCNet0.1, including mini SRCNet demonstrator services and the Rucio storage element.

      Attachments

        Issue Links

          Structure

            Activity

              People

                r.bolton Bolton, Rosie
                M.Parra Parra, Manuel
                Votes:
                0 Vote for this issue
                Watchers:
                1 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (100.00%)

                  Feature Estimate: 2.0

                  IssuesStory Points
                  To Do00.0
                  In Progress   00.0
                  Complete619.0
                  Total619.0