This feature represents non-feature contributions to Capability Low-C1 (SS-108).
- (0.5 FP) Perentie capacity reservation to support CSP with bug fixes, etc.
- (6 FP) TOPIC: see linked must have tickets
- 9.25 SP for Should have tickets not included in the size of this feature.
- (4 FP) MCCS:
- (2 FP) Support Wombat in resolving PaSD driver issues. Integration and validation of PaSD lower level driver interface to MCCS Tango devices and resolving any issues so that monitoring health status of PaSD is available and can be archived.
- (1.5 FP) Improve existing test suite to enable AIV to integrate and test MCCS in ITF
- (0.5 FP) Capacity reservation to support AIV in the ITF testing.
- <Feature
SP-3964directly linked toSS-108describes the TMC MCCS integration- Beam control to be delivered for AAVS3 in SP-3870 expected to be useful for the ITF release >
- Viola (4 FP):
- Completion of PI20 Digital Chain Tests (Including Jupyter NBs and Dry Run)
- Preparation for PI21 Digital Chain / Engineering Model Tests (Including Jupyter NBs and Dry Run)1
- Support for running PI21 Digital Chain / EM Tests (Including Test Setup/ Preparation, running of Test and post-processing support)
- Support for formal reviews / milestones (Ready Review, Test Readiness Review , Post-Test Reviews ETC) 2
1 This is dependent on Releases TAIV-791 and TAIV-827 being planned for PI21 and meeting release timelines.
2 This will only require team representation, not full team commitment