Details
-
Enabler
-
Won't have (this time)
-
None
-
LOW ART
-
-
- PTCs 3,7,11,22 all pass
- Correlator can process more than 16 stations
- CNIC time gating is complete
-
6
-
0
-
Team_PERENTIE
-
Sprint 4
-
-
-
21.6
-
-
Team_PERENTIE
-
Low G4
Description
- Complete the Correlator Perentie Test Cases #3,5,7,22
- Work on completing the AA1 correlator for the spec of 512 substations (PTC#22)
- Implement the work around for testing substations in the delay polynomial simulator (or see what TMC supply in PI#21)
- Test the 0.283s correlator integration mode? (PTC#3,11)
- Check delay tracking functions as expected for substations (PTC#11)
- Complete the CNIC time gating functionality as test correlator timestamps (PTC#7)