LOW CBF RFI Flagging Plan and Review

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Obs Mgt & Controls
      • The LOW CBF RFI plan and algorithms are known in advance of each AA
      • All flagging algorithm techniques are shared early
      • Control of LOW CBF RFI flagging is developed and shared with CSP LMC
    • Hide
      • There is a RFI flagging plan - from start to finish of construction
      • There are details for each part of the RFI flagging algorithm
      • There are LMC controls for each part of the RFI flagging algorithm
      • Estimate the effort required to implement each part of the algorithm in terms of software and firmware
      • The RFI flagging plan is reviewed and accepted by SKAO
      Show
      There is a RFI flagging plan - from start to finish of construction There are details for each part of the RFI flagging algorithm There are LMC controls for each part of the RFI flagging algorithm Estimate the effort required to implement each part of the algorithm in terms of software and firmware The RFI flagging plan is reviewed and accepted by SKAO
    • 1.5
    • 1.5
    • 0
    • Team_PERENTIE
    • Sprint 5
    • Hide

      The Draft LOW CBF RFI Processing Plan is created here:
      https://docs.google.com/document/d/1MfkrFvH-Eu3sLyde5OtH9k_-wrvxXxfte_-mxQ0u4uo/edit#heading=h.k2ws1n2q79p5

      We have concluded the RFI-related activities for PI#20. Nevertheless, we recognise that the planning and implementation of RFI processing will continue into PI#21.

      Show
      The Draft LOW CBF RFI Processing Plan is created here: https://docs.google.com/document/d/1MfkrFvH-Eu3sLyde5OtH9k_-wrvxXxfte_-mxQ0u4uo/edit#heading=h.k2ws1n2q79p5 We have concluded the RFI-related activities for PI#20. Nevertheless, we recognise that the planning and implementation of RFI processing will continue into PI#21.
    • Team_PERENTIE

    Description

      • Create a document/presentation describing the LOW CBF RFI flagging
      • Develop a detailed rollout plan for RFI flagging for each AA
      • Consider how the RFI flagging affects the beamformer and correlator
      • Discuss the details of each LOW CBF RFI flagging algorithm
      • Consider the test cases for each part of the algorithm, e.g., PTC#18

      Attachments

        Structure

          Activity

            People

              m.waterson Waterson, Mark
              y.chen Chen, Yuqing
              Votes:
              0 Vote for this issue
              Watchers:
              3 Start watching this issue

              Feature Progress

                Story Point Burn-up: (100.00%)

                Feature Estimate: 1.5

                IssuesStory Points
                To Do00.0
                In Progress   00.0
                Complete912.0
                Total912.0