CSP Low Delivery to sITF

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Enabler
    • Should have
    • PI19
    • None
    • Obs Mgt & Controls
    • 1
    • 1
    • 0
    • Team_TOPIC
    • Sprint 5
    • Hide

      Achieved; all hardware was procured and shipped. Reception of the shipments have been acknowledged by ITF/Felipe.

      Show
      Achieved; all hardware was procured and shipped. Reception of the shipments have been acknowledged by ITF/Felipe.
    • 19.6
    • Accepted by FO
    • PI24 - UNCOVERED

    • Team_TOPIC

    Description

      ITF hardware:

      • Contact Felipe Gonzalez (advised by Lucio Tirone)
      • Identify cables for ITF and SPC: send DDF to Allison/Ryan
      • procure cables for ITF
      • Send Supermicros, P4 switch, Alveo cards and cables to ITF via SKAO
      • Provide support to AIV during hardware installation PI#20 (ITF running behind)

      Attachments

        Issue Links

          Structure

            Activity

              People

                j.stoddart Stoddart, Jacque
                D.VanDerSchuur Van Der Schuur, Daniel
                Votes:
                0 Vote for this issue
                Watchers:
                3 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (100.00%)

                  Feature Estimate: 1.0

                  IssuesStory Points
                  To Do00.0
                  In Progress   00.0
                  Complete136.8999996
                  Total136.8999996