Thicken MCCS thin control slice

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Obs Mgt & Controls
    • Hide

      Assembly of Tiles functioning together to form a Station and the addition of beam-formed data streaming are necessary steps to implementation of AAVS control. 

      Show
      Assembly of Tiles functioning together to form a Station and the addition of beam-formed data streaming are necessary steps to implementation of AAVS control. 
    • Hide

      User interaction with MCCS deployed at AAVS proceeds as follows:

      • >1 (ideally 16) tiles are initialized and configured as necessary
      • These tiles are used to form a station 
      • Meaningful health attributes for all tiles are reported through a UI
      • Meaningful health attributes aggregated as a Station are reported through a UI
      • Station beam-formed data are streamed to a DAQ-to-file receiver
      • Appropriate meta-data are associated with received files
      Show
      User interaction with MCCS deployed at AAVS proceeds as follows: >1 (ideally 16) tiles are initialized and configured as necessary These tiles are used to form a station  Meaningful health attributes for all tiles are reported through a UI Meaningful health attributes aggregated as a Station are reported through a UI Station beam-formed data are streamed to a DAQ-to-file receiver Appropriate meta-data are associated with received files
    • 4
    • 4
    • 0
    • Team_MCCS
    • Sprint 5
    • Hide

      With this feature we concentrated on refining and enhancing our deployments to hardware-facing sites. The Oxford site is generally used for trials and AAVS has been used for demonstrations and to try full-station-scale operation (i.e. 16 tiles).
      Top-to-bottom control charting was developed to facilitate deployment and guide documentation produced.
      Taranta performance issues were experienced when developing dashboards for the Station with 16 Tile devices, and suitable presentation techniques in view of this developed.
      Functional tests covering the "thin slice" functionality were developed.
      At this point the new sps Station functionality was not sufficiently mature that the notebooks could drive Station beams, so this will be carried into PI18. This also meant that the demo concentrated on Tiles rather than the Station dashboard.

      Show
      With this feature we concentrated on refining and enhancing our deployments to hardware-facing sites. The Oxford site is generally used for trials and AAVS has been used for demonstrations and to try full-station-scale operation (i.e. 16 tiles). Top-to-bottom control charting was developed to facilitate deployment and guide documentation produced. Taranta performance issues were experienced when developing dashboards for the Station with 16 Tile devices, and suitable presentation techniques in view of this developed. Functional tests covering the "thin slice" functionality were developed. At this point the new sps Station functionality was not sufficiently mature that the notebooks could drive Station beams, so this will be carried into PI18. This also meant that the demo concentrated on Tiles rather than the Station dashboard.
    • 17.6
    • Stories Completed, Integrated, Solution Intent Updated, BDD Testing Passes (no errors), Outcomes Reviewed, NFRS met, Demonstrated, Satisfies Acceptance Criteria, Accepted by FO
    • PI23 - UNCOVERED

    • SYSTEM_DEMO_4 SYSTEM_DEMO_5 Team_MCCS goal_O5 mccs_software
    • SPO-2126

    Description

      The PI16 "thin control slice" establish minimal end-to-end hardware control functionality, causing a single TPM to stream Voltage data to a DAQ-to-file receiver and thence to file.

      This feature describes "thickening" this slice by adding greater functionality.

      The control script (Jupyter notebook) for the "thin slice" took the place of station-forming operations. In this feature we will implement this in the Station device itself. We will add more capability to the Tile device, implementing fully tile configuration.

      Refine this section during planning. Select options from:

      • Station formation in the Station devices, includes:
        • TPM synchronization
        • TPM base configuration (e.g. setting IPs to establish the data daisy chain)
      • Complete the connexions for Configure()
      • Add beam-formed data collection
        • Initially default to zenith drift scan
        • Stretch goal - Implement beam pointing

      Attachments

        Issue Links

          Structure

            Activity

              People

                a.bridger Bridger, Alan
                S.Melhuish Melhuish, Simon
                Votes:
                0 Vote for this issue
                Watchers:
                1 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (100.00%)

                  Feature Estimate: 4.0

                  IssuesStory Points
                  To Do00.0
                  In Progress   00.0
                  Complete1633.0
                  Total1633.0