      We need an equipment list for procurement. The equipment list will allow procurement to proceed in timescales to meet the AA0.5 deployment.

      Show
      We need an equipment list for procurement. The equipment list will allow procurement to proceed in timescales to meet the AA0.5 deployment.
    • Hide

      Tech Spec produced for PM/Procurement to progress

      Recommendations provided to PM/Procurement

      Show
      Tech Spec produced for PM/Procurement to progress Recommendations provided to PM/Procurement
    • 1
    • 1
    • 0
    • Team_SKANET
    • Sprint 5
    • Hide

      This procurement is not yet complete, but it is now being handled through the framework agreement by the networks & computing PM, minimal support is required from team SKANET so requested by RTE & PM to cover remaining support as standalone stories and to close this feature.

       

      Show
      This procurement is not yet complete, but it is now being handled through the framework agreement by the networks & computing PM, minimal support is required from team SKANET so requested by RTE & PM to cover remaining support as standalone stories and to close this feature.  
    • 19.6
    • Stories Completed, Accepted by FO
    • PI23 - UNCOVERED

    • SPO-2508

    Description

      Networks (assume buy own kit) specs for LOW AA0.5 (Must be under €200,000) - given current lead times this should have some priority in PI18.

      Technical specification to include all standards required and EMI/RFI  and environmental requirements to be met.

      Including the required spares, support and any installation configuration expertise required.

      Attachments

        Issue Links

          Structure

            Activity

              People

                m.deegan Deegan, Miles
                N.Quinn Quinn, Neil
                Votes:
                0 Vote for this issue
                Watchers:
                0 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (100.00%)

                  Feature Estimate: 1.0

                  IssuesStory Points
                  To Do00.0
                  In Progress   00.0
                  Complete511.0
                  Total511.0

                  Dates

                    Created:
                    Updated:
                    Resolved: