      This will ensure that the network related details and interfaces associated with various contracts is accurately reflected in documentation and instruction to be given to potential vendors/bidders.

      Show
      This will ensure that the network related details and interfaces associated with various contracts is accurately reflected in documentation and instruction to be given to potential vendors/bidders.
    • Hide

      That networks have provided satifactory attendance and input to all the CRRs, as requested, in PI14.

      Show
      That networks have provided satifactory attendance and input to all the CRRs, as requested, in PI14.
    • Inter Program
    • 1
    • 1
    • 0
    • Team_PLANET
    • Sprint 5
    • Overdue
    • Hide

      The PMs with CRRs in PI14 that have a reliance on networks either as an interface or as an integral part of their design, have had  suitable scrutiny on their contractual documentation relating to networks.

      Show
      The PMs with CRRs in PI14 that have a reliance on networks either as an interface or as an integral part of their design, have had  suitable scrutiny on their contractual documentation relating to networks.
    • PI22 - UNCOVERED

    Description

      Provide a review of networks aspects of the various contracts due to hold a CRR in PI14. Review documentation as presented and provide comments and questions for the relevant PM in sufficient time for the CRR event.

      Attend or otherwise participate in the CRR.

      Provide any follow up information /actions as a result of the CRR.

      Attachments

        Structure

          Activity

            People

              m.deegan Deegan, Miles
              j.hammond Hammond, Jill
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

              Feature Progress

                Story Point Burn-up: (0%)

                Feature Estimate: 1.0

                IssuesStory Points
                To Do00.0
                In Progress   00.0
                Complete00.0
                Total00.0