Uploaded image for project: 'SAFe Program'
  1. SAFe Program
  2. SP-2412

Create a new DDD for MID based on the changes made for ECP-200048

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Feature
    • Must have
    • PI14
    • None
    • None
    • Services
    • Hide

       The baseline design for MID networks will be a clear and accurate document to provide for tenderers to submit against.

      Show
       The baseline design for MID networks will be a clear and accurate document to provide for tenderers to submit against.
    • Hide

      A new MID Networks DDD is uploaded into ALIM.

      All PMs with products that interface MID networks  are aware of the new document so that they  can reflect this in the relevant other documentation.

      Show
      A new MID Networks DDD is uploaded into ALIM. All PMs with products that interface MID networks  are aware of the new document so that they  can reflect this in the relevant other documentation.
    • Intra Program
    • 2
    • 0
    • Sprint 5
    • Overdue
    • Hide

      New document available.

      Show
      New document available.
    • PI22 - UNCOVERED

    Description

      The current baseline DDD for MID networks was written in 2018 prior to several significant ECPs that have significantly changed the MID networks design. it is unfeasible to give tenderers this document and ECPs and expect them to align the 2. Hence the DDD needs rewriting to align with the heavily modified design and ensure that there is no ambiguity for tenderers.

      This document will replace the current baseline design document.

      Attachments

        Structure

          Activity

            People

              m.deegan Deegan, Miles
              j.hammond Hammond, Jill
              Votes:
              0 Vote for this issue
              Watchers:
              0 Start watching this issue

              Feature Progress

                Story Point Burn-up: (0%)

                Feature Estimate: 2.0

                IssuesStory Points
                To Do00.0
                In Progress   00.0
                Complete00.0
                Total00.0

                Dates

                  Created:
                  Updated:

                  Structure Helper Panel