IGO HQ External Network Planning and Preparation

Details

    • Feature
    • Must have
    • PI12, PI13
    • None
    • Services
    • Hide

      An independent IGO-contracted link will be available to provide the assurance of independent communications links for the IGO HQ once cutover achieved.

      Remaining UoM services will be better understood allowing for an easier separation and independent contracting for these services in future months.

      Planning will greatly increase the likelihood of a swift cutover with minimal disruption.

       

      Show
      An independent IGO-contracted link will be available to provide the assurance of independent communications links for the IGO HQ once cutover achieved. Remaining UoM services will be better understood allowing for an easier separation and independent contracting for these services in future months. Planning will greatly increase the likelihood of a swift cutover with minimal disruption.  
    • Hide

      Openreach handover of service to Jisc

      Cutover plan with steps established and agreed by all parties

      Secondary link to UoM prepared and IP and other required changes designed and agreed with UoM

      Jisc service failover design produced and required improvements/implementations documented as future tasks

       

      Show
      Openreach handover of service to Jisc Cutover plan with steps established and agreed by all parties Secondary link to UoM prepared and IP and other required changes designed and agreed with UoM Jisc service failover design produced and required improvements/implementations documented as future tasks  
    • 2
    • 2
    • 0
    • Team_IT
    • Sprint 5
    • Hide

      Openreach handed service to Jisc on installation of final monitoring line.

      Cutover plan was agreed by all parties

      Secondary link to UoM prepared and IP and other required changes designed and agreed with UoM - but this did not function as desired and was abandoned in cutover.

      Jisc service failover design produced and further improvements are in the backlog.

       

      Show
      Openreach handed service to Jisc on installation of final monitoring line. Cutover plan was agreed by all parties Secondary link to UoM prepared and IP and other required changes designed and agreed with UoM - but this did not function as desired and was abandoned in cutover. Jisc service failover design produced and further improvements are in the backlog.  
    • 15.6
    • Stories Completed, Integrated, Outcomes Reviewed, Demonstrated, Satisfies Acceptance Criteria, Accepted by FO
    • PI22 - UNCOVERED

    • Team_IT

    Description

      The preparatory work required to be ready to invoke a successful cutover of Internet and other NREN-related services onto the new Jisc resilient fibre connection and away from the University of Manchester (UoM) -supplied service.

      As well as preparing for cutover we will need to design and implement a secondary link to allow continued connectivity to the UoM network (estimating needing this for up to a year from commission) to allow the continued operation of UoM-controlled building management elements (such as door access, environmental controls, lighting). This will need to be done in cooperation with UoM IT Services and the outsourced network support company Roc who handle Local Area Network services for UoM.

      Proposed cutover steps, firewall changes and IP range migration, establishing replacement IPs for the secondary link, EduROAM design and initial build and failover design for the new service will also be needed and this will have to include UoM, Jisc and Team_IT and possibly some input from members of PLANET.

      Due to proposed timescales from Jisc/Openreach the final stages of the resilient link installation are likely to be undertaken in Iterations 1 and 2 but this will be handled in an existing SIT Task with a dependency set for any Stories linked to this Feature as appropriate. Some of this Feature is not dependent so a relates to link has been created for reference here.

      Attachments

        Structure

          Activity

            People

              r.schofield Schofield, Richard
              r.schofield Schofield, Richard
              Votes:
              0 Vote for this issue
              Watchers:
              0 Start watching this issue

              Feature Progress

                Story Point Burn-up: (100.00%)

                Feature Estimate: 2.0

                IssuesStory Points
                To Do00.0
                In Progress   00.0
                Complete821.0
                Total821.0