Implement version controlling of PSS test vectors and pipeline configuration files

Change Owns to Parent OfsSet start and due date...
    XporterXMLWordPrintable

Details

    • Data Processing
    • Hide

      Version control of test vectors and configuration files will ensure that the testing framework is always run on the appropriate set of files, and enables roll-back to earlier versions if issues are encountered. 

      Show
      Version control of test vectors and configuration files will ensure that the testing framework is always run on the appropriate set of files, and enables roll-back to earlier versions if issues are encountered. 
    • Hide

      Version control of test vectors has been added to the PSS Test Vector Generator. Naming convention of Cheetah configuration files has been agreed and documented.  

      Show
      Version control of test vectors has been added to the PSS Test Vector Generator. Naming convention of Cheetah configuration files has been agreed and documented.  
    • 3
    • 3
    • 8
    • 2.667
    • Team_PSS
    • Sprint 3
    • Hide

      DP ART 12.5 Demo presentation: Updates to Test Vector Generator.pptx.pdf

      Show
      DP ART 12.5 Demo presentation:  Updates to Test Vector Generator.pptx.pdf
    • 12.3
    • Stories Completed, Outcomes Reviewed, NFRS met, Satisfies Acceptance Criteria, Accepted by FO
    • PI24 - UNCOVERED

    • Team_PSS

    Description

      Add functionality to the PSS Test Vector Generator ensuring that the resulting test vectors are version controlled. Include discussion on naming conventions and version control mechanisms for configuration files. 

       

      Attachments

        Issue Links

          Structure

            Activity

              People

                A.Noutsos Noutsos, Aristeidis
                m.pearson Pearson, Mike [X] (Inactive)
                Votes:
                0 Vote for this issue
                Watchers:
                3 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (100.00%)

                  Feature Estimate: 3.0

                  IssuesStory Points
                  To Do00.0
                  In Progress   00.0
                  Complete521.0
                  Total521.0