Feature
-
Won't have (this time)
-
None
-
Obs Mgt & Controls
-
-
5
-
1
-
-
Overdue
Description
Prepare for delivery of TPM1.6 in Q2, 21 including configured 100G switch, power and cooling control (at least check its on) and updated Tile device driver.
(Initial test can could hack existing AAVS scripts using TPM1.2, so may not be so much dev work but do need QA (DoD) work on that)
Developing Tests strategy and concepts
Include rich colaboration with MCCS firmware team, Perentie and Team Viola to prepare and execute this.
*possibly want to invite networks/Platform (PLANET) to help observe/document (only) this test? Deegan, Miles Lloyd, Samantha Lewis, Peter Hammond, Jill
Attachments
Issue Links
- relates to
-
SP-1397 Connect to TPM hardware (1.2) in PSI
- Done