Uploaded image for project: 'SAFe Program'
  1. SAFe Program
  2. SP-1112

Resolve outstanding issues from adding 1GB network connection to SPS network

Details

    • Feature
    • Not Assigned
    • PI7
    • None
    • Services
    • Hide

      A design as agreed by the TDT technical specialist.

      Show
      A design as agreed by the TDT technical specialist.
    • 0.5
    • 2
    • 0
    • Team_PLANET
    • Sprint 5
    • Hide

      All outstanding issues addressed.

      Show
      All outstanding issues addressed.
    • 8.3
    • Stories Completed, Outcomes Reviewed, Satisfies Acceptance Criteria, Accepted by FO
    • PI22 - UNCOVERED

    Description

      This is the TDT-LOW team request to continue with the work done in the last PI to re- design a network end to end solution.

      Attachments

        Issue Links

          Structure

            Activity

              People

                m.waterson Waterson, Mark
                j.hammond Hammond, Jill
                Votes:
                0 Vote for this issue
                Watchers:
                2 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (100.00%)

                  Feature Estimate: 0.5

                  IssuesStory Points
                  To Do00.0
                  In Progress   00.0
                  Complete22.0
                  Total22.0

                  Dates

                    Created:
                    Updated:
                    Resolved: