Uploaded image for project: 'SAFe Program'
  1. SAFe Program
  2. SP-1111

Summarise design concepts, project impact and plan of work to incorporate a DDBH detailed design into the LOW Network.

Details

    • Feature
    • Not Assigned
    • PI7
    • None
    • Services
    • Hide

      The LOW TDT require a solution to the current design void as soon as is possible, within the constrained budget from the CCP event.

      Show
      The LOW TDT require a solution to the current design void as soon as is possible, within the constrained budget from the CCP event.
    • Hide

      A design agreed to by the TDT LOW PM to be taken forward for the end-to-end network design.

      Show
      A design agreed to by the TDT LOW PM to be taken forward for the end-to-end network design.
    • 2
    • 2
    • 0
    • Team_PLANET
    • Sprint 5
    • 7.5
    • PI22 - UNCOVERED

    • Team_PLANET

    Description

      Review the current overall LOW design for the Receptor to CBF and design the end-to -end Network solution.
      TRKECP-71

      Attachments

        Structure

          Activity

            People

              a.vanes van Es, Andre
              j.hammond Hammond, Jill
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

              Feature Progress

                Story Point Burn-up: (100.00%)

                Feature Estimate: 2.0

                IssuesStory Points
                To Do00.0
                In Progress   00.0
                Complete613.0
                Total613.0

                Dates

                  Created:
                  Updated:
                  Resolved: