This is to decide architecture-level enablers, and think about implications:
- Determine the “real” nature of StationBeam (is “hardware-like” Tango object correct?)
- Figure out how to manage the asynchronous processes without involving the TM-level scheduler
- Elaborate the resource-management functions & where/how they will be implemented
- Clarify low-power support
- Clarify the nature of "antenna" device - mapping to power control, static attributes
- (longer-term/lower priority) What is the implementation of TransientBuffer going to involve? TransientVoltageBuffer?
Outcomes:
- ADR decisions as needed to document outcome of investigations
- Features to implement changes or definitions