Details
-
PI Risk
-
Resolution: Done
-
None
-
Program
-
Obs Mgt & Controls
-
Team_MCCS, Team_NCRA, Team_SYSTEM
-
Resolved
Description
Delay in availability of SKA LOW integration environment for early integration testing of TMC and MCCS - NCRA
Mitigation plan discussed by System, MCCS, NCRA. System team will deliver helm chart related major decisions by start of Sprint 3 enabling NCRA to work in the remaining Sprint 3 and Sprint 4. Checkpoints on the progress of this plan will happen during SoS /PO syncs.
Progress to be reported and demo'd at ST sprint review at end of sprint 2, with NCRA team invited. Date TBC, probably 6/7 Oct.
Attachments
Issue Links
- relates to
-
SP-1241 Define the architecture of helm subcharts and repositories
- Done