Uploaded image for project: 'SAFe Program'
  1. SAFe Program
  2. SP-1473

Draft ECP-200048 Implementation Plan

Details

    • Enabler
    • Not Assigned
    • PI9
    • None
    • Services
    • Hide

      Aid implementation of the ECP (Movement of MID CSP from site to the SPC)

      Help ensure that relevant documents are changed in time for procurement.

      Show
      Aid implementation of the ECP (Movement of MID CSP from site to the SPC) Help ensure that relevant documents are changed in time for procurement.
    • Hide

      Plan is documented in Confluence.

      CM and TDT MID accept the plan.

      Show
      Plan is documented in Confluence. CM and TDT MID accept the plan.
    • 0.5
    • 0
    • Team_PLANET
    • Sprint 4
    • 9.6
    • PI22 - UNCOVERED

    Description

      Work with ECP sponsor (m.miccolis) and CM (s.nel) to draft an Implementation Plan and identify areas of work required and when this work needs to be completed by.

      https://confluence.skatelescope.org/display/CMI/ECP-200048+%28former+ECP-190009%29+-+Movement+of+MID+CSP+from+site+to+the+SPC 

      Attachments

        Structure

          Activity

            People

              m.deegan Deegan, Miles
              m.deegan Deegan, Miles
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

              Feature Progress

                Story Point Burn-up: (100.00%)

                Feature Estimate: 0.5

                IssuesStory Points
                To Do00.0
                In Progress   00.0
                Complete11.0
                Total11.0

                Dates

                  Created:
                  Updated:
                  Resolved: