Review compute requirements (rollout plan) for AA0.5 - AA3

Details

    • Enabler
    • Not Assigned
    • PI9
    • None
    • Services
    • Hide

      Ensure that documentation is in good shape prior to procurement. This includes matters such as power requirements. Also needed in order to update MID SPC Requirements to reflect the changes from ECP-2000048.

      Show
      Ensure that documentation is in good shape prior to procurement. This includes matters such as power requirements. Also needed in order to update MID SPC Requirements to reflect the changes from ECP-2000048.
      • Produce new estimate of numbers of servers, numbers of racks, "footprint" and power consumption for SDP, PSS and PST for AA0.5, 1, 2, 3.
    • 1
    • 1
    • 40
    • Team_PLANET
    • Sprint 5
    • Overdue
    • PI22 - UNCOVERED

    • Team_PLANET

    Description

      Reassess the sizes of "milli-SDP" and "centi-SDP" looks like for AA0.5-AA3 and whether or not these assumptions are still applicable. Use parametric model for this. Review PSS and PST system sizes.

      If necessary, update documents that list rack budgets, power etc. Ensure requirements for SPC MID are updated to reflect these changes in light of ECP-2000048.

      Attachments

        Issue Links

          Structure

            Activity

              People

                m.deegan Deegan, Miles
                r.brederode Brederode, Ray
                Votes:
                0 Vote for this issue
                Watchers:
                2 Start watching this issue

                Feature Progress

                  Story Point Burn-up: (100.00%)

                  Feature Estimate: 1.0

                  IssuesStory Points
                  To Do00.0
                  In Progress   00.0
                  Complete47.0
                  Total47.0

                  Dates

                    Created:
                    Updated: